US Navy Cancels Biden-Era Submarine Contract as Overhaul Costs Approach $3 Billion
TL;DR
The U.S. Navy has decided to inactivate the USS Boise, a Los Angeles-class attack submarine that sat pier-side for over a decade, after spending nearly $800 million on an overhaul that reached only 22% completion. The cancellation of a Biden-era $1.2 billion repair contract with HII Newport News Shipbuilding — which would have ballooned total costs toward $3 billion — reflects both a rare act of fiscal discipline and a damning indictment of the Navy's chronic inability to maintain its submarine fleet.
On April 10, 2026, Navy Secretary John Phelan confirmed what defense analysts had expected for months: the USS Boise (SSN-764), a Los Angeles-class nuclear attack submarine commissioned in 1992, will be permanently inactivated . The vessel has not operated at sea since 2015, lost its dive certification in 2017, and consumed nearly $800 million in taxpayer funds while sitting in a Virginia shipyard with only 22% of its scheduled overhaul work completed .
"We screwed up. We did. This doesn't look good. It is what it is. Time to move on," Phelan told Semafor .
The decision kills a $1.2 billion engineering overhaul contract awarded to Huntington Ingalls Industries' Newport News Shipbuilding division in February 2024 — a contract that was itself nine years behind schedule when it was signed . Had the Navy stayed the course, total lifecycle costs for the Boise overhaul were projected to approach $2.7 billion, with completion unlikely before 2029 at the earliest . The submarine would have returned to service with roughly 20% of its operational life remaining — enough for approximately three deployments .
The Contract: A Decade of Delay
The Boise's overhaul was originally scheduled to begin in fiscal year 2016 at Norfolk Naval Shipyard, one of four public shipyards that handle nuclear submarine maintenance . But Norfolk was consumed by higher-priority work: ballistic missile submarine refuelings and aircraft carrier repairs. The Boise was effectively placed in a queue that never moved.
In 2018, the Navy transferred the Boise to HII's Newport News Shipbuilding in an effort to break the logjam, paying $351.8 million in initial planning and preparatory work . Newport News had not performed a submarine overhaul in over a decade and needed years to reconstitute its submarine repair capabilities . The work never started in earnest. By 2021, the Chief of Naval Operations stated the overhaul would begin "soon" — it did not .
The formal $1.2 billion contract was finally awarded on February 23, 2024, covering "maintenance and restoration of the ship's hull structure, tanks, propulsion systems, electric plant, auxiliary systems, armament and furnishings, as well as numerous ship alterations" . The contract estimated completion by September 2029 — fourteen years after the Boise's last deployment.
What Drove Costs Toward $3 Billion
The Boise's cost explosion was not caused by a single failure but by compounding problems that were largely foreseeable at the time of contract award.
Deferred maintenance compounding. The longer a nuclear submarine sits idle, the more its systems degrade. Rubber seals, gaskets, and pipe linings deteriorate. Electronics corrode. By the time work began in earnest, the scope of repairs had expanded far beyond the original engineering estimates .
Labor shortages. The submarine industrial base faces a structural workforce crisis. The Navy needs to hire 100,000 new skilled trade workers over the next decade . At HII's shipyards, 57% of trade workers have fewer than five years of experience, requiring more supervision and producing more rework . The Navy's recruiting pipeline for shipyard workers loses more than half of new hires within their first year, largely because wages cannot compete with private-sector manufacturing and service jobs .
Supply chain failures. Specialized submarine components are produced by a narrow base of suppliers, many of whom face their own workforce and capacity constraints. Delays in material delivery cascaded through the project timeline .
Cost-plus contract structure. The Boise overhaul, like much of the Navy's maintenance work, operated under cost-plus contracting, where the government reimburses a contractor for all allowable costs and then pays an additional fee for profit. This structure, as the Government Accountability Office has documented repeatedly, creates weak incentives for contractors to control costs. Under cost-plus arrangements, companies are reimbursed for escalating expenses, and hours spent on tasks "magically inflate once the work starts," as Breaking Defense described the dynamic . The GAO has found that the Department of Defense paid an estimated $8 billion in award and incentive fees across contracts "regardless of whether acquisition outcomes fell short of, met, or exceeded DOD's expectations" .
Reconstituting lost capability. Newport News Shipbuilding had a ten-year gap in submarine overhaul work before taking on the Boise. Rebuilding institutional knowledge and tooling took years and added cost .
HII's Track Record
Huntington Ingalls Industries is one of only two companies in the United States that build nuclear-powered submarines, alongside General Dynamics Electric Boat. Together, they have built and delivered 24 Virginia-class submarines . HII's Newport News division has completed refueling and complex overhauls on six Nimitz-class aircraft carriers and is currently working on a seventh .
But the company's submarine work has faced consistent challenges. Virginia-class production runs at roughly 60% of its annual goal, years behind schedule, due to workforce and capacity constraints . HII CEO Chris Kastner acknowledged in late 2025 that existing submarine funding approaches were "insufficient to get boats the Navy wants" .
In response to the Boise cancellation, HII spokesperson Todd Corillo stated the company anticipates "no impact to our workforce and will transition shipbuilders currently assigned to USS Boise to other work underway at Newport News Shipbuilding" . This is a significant claim: HII is currently engaged in Virginia-class and Columbia-class construction work, and the workers freed from the Boise project represent scarce skilled labor the company needs elsewhere.
The Math: Overhaul vs. New Build
The Boise's projected $2.7 billion overhaul cost demands comparison with other options. A typical Los Angeles-class Engineered Refueling Overhaul costs roughly $400 million . A new Virginia-class submarine costs approximately $5 billion under the Navy's FY2026 budget submission . A Columbia-class ballistic missile submarine — a different mission set entirely — runs about $10.5 billion .
The Boise overhaul would have cost roughly 65% of a new Virginia-class submarine, according to Fox News reporting, yet would have returned a 1990s-era boat with limited remaining service life . A new Virginia-class submarine offers 33 years of service and significantly greater capability. By that arithmetic, the Navy's decision to walk away looks less like waste and more like triage.
For international comparison, nuclear submarine refueling and overhaul costs for allied navies provide limited benchmarks. UK Astute-class and Trafalgar-class submarines use highly enriched uranium reactors that do not require mid-life refueling, reducing their overhaul complexity . France's Rubis-class and Suffren-class submarines use low-enriched uranium reactors that require refueling approximately every ten years, a process that takes about six months and costs significantly less than a full American ERO . Neither the UK nor France has experienced overhaul cost escalation at the scale of the Boise.
Fleet Readiness: The Operational Toll
The Boise's inactivation removes one attack submarine from the Navy's nominal order of battle, but the vessel has been operationally useless since 2015. The real question is what the decision signals for the broader fleet.
The Navy currently has 17 fast-attack submarines in public shipyards . Attack submarine idle time — the days submarines spend waiting to enter maintenance or delayed in completing it — has escalated sharply over the past decade. From fiscal year 2016 through fiscal year 2025, inactive attack submarines accumulated 3,287 days of idle time, peaking at 1,260 days in FY2025 alone . Without mitigation, the GAO projects 15 attack submarines will enter inactive idle time through fiscal year 2030, accumulating more than 14,000 idle days .
The Navy spent $4.2 billion on attack submarines sitting idle between FY2016 and FY2025 — paying crews, maintaining pier-side infrastructure, and supporting boats that could not deploy . Chief of Naval Operations Admiral Daryl Caudle described the maintenance situation as "like a dagger in the heart" for the submarine force .
The Navy's goal is to have 80% of its fleet ready to deploy by 2027, a target that requires strict adherence to maintenance schedules . Canceling the Boise does not directly worsen this metric — the boat was never going to be available by 2027. But it does reduce the total number of attack submarines the Navy can field in the 2030s, at a time when China's submarine fleet continues to grow.
Two additional Los Angeles-class boats — USS Newport News (SSN-750) and USS Alexandria (SSN-757) — are also scheduled for inactivation in 2026 and will be scrapped at Puget Sound Naval Shipyard .
The Workforce Question
The Navy plans to redirect workers from the Boise project to Virginia-class and Columbia-class submarine construction . This is consistent with broader industrial strategy: the FY2027 budget request includes $11.4 billion for two Virginia-class submarines and $10.5 billion for one Columbia-class submarine .
HII's assertion that no workers will be laid off is plausible given the scale of competing demands for skilled submarine labor. Newport News currently employs approximately 25,000 workers, and the facility is engaged in carrier and submarine work simultaneously . The constraint on submarine production has never been too many workers — it has been too few.
The broader shipyard workforce picture remains difficult. The Navy is investing nearly $1 billion in automated manufacturing facilities designed to produce submarine parts faster and with fewer workers . The Shipyard Infrastructure Optimization Program, a multi-decade effort to modernize the four public naval shipyards, continues with contracts like a $377 million upgrade to Dry Dock 4 at Puget Sound .
The Case for Cancellation as Fiscal Discipline
The strongest argument for the Navy's decision is the simplest: finishing the Boise would have rewarded a broken system.
Cost-plus contracting has a documented history of insulating contractors from the consequences of cost growth. The GAO has repeatedly found that DOD pays billions in incentive fees without regard to whether contracts meet their cost or schedule targets . Completing the Boise overhaul — spending an additional $1.9 billion to recover a submarine that would serve for a few more years — would have set a precedent that there is no cost threshold at which the Navy will walk away from a failing project.
"By killing these programs, it's sending a message that we're not going to continue to send good money after bad investments," Phelan said .
This framing has supporters. Defense reformers have long argued that the Pentagon's unwillingness to cancel troubled programs creates a moral hazard: contractors and program offices know that once spending passes a certain threshold, political inertia will carry the project to completion regardless of performance. The Boise cancellation breaks that pattern.
Critics counter that the cancellation penalizes the wrong party. The submarine sat idle for nearly a decade not because HII failed to perform, but because the Navy's public shipyards could not accommodate it. By the time the contract was awarded in 2024, costs had already ballooned due to the Navy's own scheduling failures. Canceling the contract after the fact does not address the root causes — underfunded shipyard capacity and chronic workforce shortfalls — that created the problem .
Accountability and the Revolving Door
The officials who presided over the Boise's decade of drift span multiple administrations and Navy leadership teams. The submarine's overhaul was originally deferred during the Obama administration, remained stalled through the first Trump administration, was contracted during the Biden administration, and has now been canceled during the second Trump administration. No single official bears responsibility for the cumulative failure.
Navy Secretary Phelan, who made the cancellation decision, comes from the private equity world rather than the defense establishment. He co-founded MSD Capital, which manages the wealth of Michael Dell, and holds investments worth over $50 million in Dell Technologies — a company with a $2.5 billion Navy contract . Senator Elizabeth Warren raised concerns about Phelan's potential conflicts of interest during his confirmation process, urging him to divest defense contractor holdings . Phelan was confirmed by the Senate 62-30 in March 2025 .
The broader pattern of defense industry revolving doors remains intact. A 2023 Project on Government Oversight investigation found that hundreds of senior Pentagon officials move to defense contractor positions after government service, and vice versa . Whether any officials involved in the Boise's contract decisions have made such transitions is not publicly documented.
The Golden Fleet and What Comes Next
The Boise cancellation arrives as the Trump administration pursues the most aggressive naval expansion since the Cold War. The FY2027 budget request of $65.8 billion for shipbuilding represents a 242% increase over FY2026 levels, funding 18 battle force ships and 16 support vessels . The administration's "Golden Fleet" initiative, announced by President Trump in December 2025, envisions a new class of battleships armed with lasers and hypersonic missiles, alongside expanded frigate and unmanned vessel production .
The tension is obvious: the Navy cannot maintain the fleet it has, yet is proposing to build a dramatically larger one. The Boise is a casualty of this gap between ambition and industrial capacity. Whether the Golden Fleet's shipbuilding surge will strain the same workforce and supply chains that failed the Boise — or whether the massive budget increase will finally expand capacity enough to break the cycle — remains the central unanswered question in American naval policy.
Admiral Caudle called the Boise decision "a tough but necessary decision" that would allow the Navy to prioritize delivery of Virginia and Columbia-class submarines . The math supports him. But the $800 million already spent on the Boise — money that bought 22% of an overhaul on a submarine that will never sail again — stands as a measure of what the Navy's maintenance crisis has cost and continues to cost the United States.
Related Stories
Trump Budget Requests $1.5 Trillion for Defense Alongside Deep Cuts to Domestic Programs
Senate Passes Bipartisan Housing Bill Targeting Institutional Investors
Senate Passes First Major Housing Bill Since Subprime Crisis
US and Iran Dispute Status of Submarine-Sunk Iranian Warship
Trump Proceeded with Iran War Despite Hormuz Blockade Risk
Sources (23)
- [1]Navy scraps Biden-era submarine contract as overhaul costs surge toward $3Bfoxnews.com
Reports on the Navy's decision to cancel the USS Boise overhaul contract, including cost breakdowns showing $800M spent for 22% completion and projected total costs near $3B.
- [2]Navy inactivates costly attack submarine as it pursues Trump-backed fleet overhaulsemafor.com
Navy Secretary Phelan's interview stating 'We screwed up' and describing the decision to stop sending 'good money after bad investments,' with details on Golden Fleet priorities.
- [3]Navy retires Boise nuclear sub after decade on sidelinesaxios.com
Reports Navy Secretary Phelan's statement that walking away saves billions and frees manpower, with context on the FY2027 budget of over $65 billion for shipbuilding.
- [4]Sub Boise will begin its overhaul nine years late, with $1.2B contractdefensenews.com
Details the original $1.2B contract awarded to HII Newport News in February 2024, the $351.8M in prior planning costs, and the full timeline of delays from FY2016 onward.
- [5]11 Years Of Waiting for Repairs: The Navy Has A Nuclear Attack Submarine Trapped in Port19fortyfive.com
Analysis of the Boise's extended idle period, deteriorating systems, and the compounding costs of deferred maintenance on nuclear submarine systems.
- [6]Navy to mothball USS Boise, capping off years of maintenance challengesbreakingdefense.com
HII spokesperson confirms no workforce impact, with workers transitioning to other programs. Includes FY2027 shipbuilding budget details: $11.4B for Virginia-class, $10.5B for Columbia-class.
- [7]U.S. Navy Invests Nearly $1 Billion To Automate Submarine Production Amid Workforce Shortagesmarineinsight.com
Reports on $900M Navy investment in automated manufacturing, the need for 100,000 new skilled trade workers over 10 years, and 57% of HII workers having fewer than 5 years experience.
- [8]Amid shortage, Navy recruiting program struggles to keep half first-year shipbuildersbreakingdefense.com
More than half of new shipyard recruits leave within their first year, with 9,700 hired in FY2023. Pay competitiveness cited as primary attrition driver.
- [9]US Navy ship programs face years-long delays amid labor, supply woesdefensenews.com
Virginia-class production at roughly 60% of annual goal due to workforce and capacity constraints across shipbuilders and their suppliers.
- [10]The 'Cost Plus' boondoggle that hobbles US defensebreakingdefense.com
Analysis of cost-plus contracting incentive problems, describing how hours and costs inflate under these contract structures in defense procurement.
- [11]Defense Acquisitions: DOD Has Paid Billions in Award and Incentive Fees Regardless of Acquisition Outcomesgovinfo.gov
GAO finding that DOD paid an estimated $8 billion in award fees across contracts regardless of whether outcomes met expectations.
- [12]Huntington Ingalls Industrieswikipedia.org
Background on HII as one of two nuclear submarine builders, with 24 Virginia-class submarines delivered jointly with Electric Boat, and carrier overhaul history.
- [13]Submarine Funding Anomaly Insufficient to Get Boats the Navy Wants, Says HII CEOnews.usni.org
HII CEO states existing submarine funding approaches are insufficient to meet Navy requirements for Virginia and Columbia-class submarine production.
- [14]Los Angeles-class submarinewikipedia.org
Original acquisition costs ranging from $225M in early production to $782M for the final boat. Typical Engineered Overhaul costs of approximately $400M.
- [15]Navy Virginia-Class Submarine Program and AUKUS Submarine: Background and Issues for Congresscongress.gov
Congressional Research Service report showing Virginia-class unit costs of approximately $5 billion under FY2026 budget, up from $4.5B average in FY2011-2024.
- [16]It Takes Years To Refuel A Nuclear Submarine — Here's Whybgr.com
Comparison of nuclear submarine refueling approaches: US/UK use HEU reactors lasting full service life; France uses LEU requiring refueling every 10 years at lower cost.
- [17]The U.S. Navy's Next Big Crisis: Building and Repairing Nuclear Submarines Feels Impossible19fortyfive.com
Reports 17 fast-attack submarines currently in public shipyards and the scale of the maintenance backlog facing the submarine force.
- [18]GAO-26-108888: Military Readiness - DOD Should Take Further Actions to Address Challengesgao.gov
GAO reports 3,287 idle days for attack submarines FY2016-FY2025, peaking at 1,260 in FY2025, with $4.2 billion spent supporting idle submarines and projecting 14,000 idle days through FY2030.
- [19]Navy's readiness push means longer maintenance for current shipsnavytimes.com
Navy targeting 80% fleet readiness by 2027, requiring strict adherence to maintenance schedules under NAVSEA strategy.
- [20]Navy Determines Planned Ship Inactivations for Fiscal 2026seapowermagazine.org
USS Newport News (SSN-750) and USS Alexandria (SSN-757) scheduled for inactivation in 2026, to be scrapped at Puget Sound Naval Shipyard.
- [21]John Phelan, Trump donor, businessman with no prior military experience, poised to lead the Navyfederalnewsnetwork.com
Background on Phelan's career at MSD Capital managing Michael Dell's wealth, $50M+ Dell Technologies holdings, and Sen. Warren's conflict-of-interest concerns.
- [22]Brass Parachutes: The Problem of the Pentagon Revolving Doorpogo.org
Project on Government Oversight investigation documenting hundreds of senior Pentagon officials rotating between government service and defense contractor positions.
- [23]Trump's 2027 budget request includes more than $65B for Navy shipbuildingdefensescoop.com
FY2027 shipbuilding request of $65.8 billion, a 242% increase, funding 18 battle force ships including new battleship class with lasers and hypersonic missiles.
Sign in to dig deeper into this story
Sign In